RRECL – 50 MWp Solar Tender for Government Buildings

RRECL 50 MWp Tender Rajasthan Government

On 04 September 2019, Rajasthan Renewable Energy Corporation Limited (RRECL) released the Request for Proposal (RFP) for selection of bidders for Design, Supply, Erection, Testing, Commissioning and Operation and Maintenance for 25 years of 50 MWp of Grid Connected Rooftop Solar Photovoltaic Power Projects on State Government buildings/State Government undertaking buildings in Rajasthan Under RESCO Mode (NIT No.: TN-05/2019-20).

Important Conditions / Terms:

No. of successful Bidders and their Allocated Capacity (MWp) Total 8 Nos. Successful Bidders:
8 MWp to L-1 Bidder
6 MWp (each) * 7 bidders in ascending order after matching L-1 Rates
Total Capacity50 MWp
Bid Security Rs. 72 Lacs (@ Rs 9 Lacs per MWp)
Scheduled Commercial Operation Date (SCOD)SCOD shall mean 24 months from thedate of Issuance of LoA.
Tariff BiddingBidder to provide the Quoted Fixed Tariff up to 4 decimal places.
Term 25 Years

Important Dates:

Period of Downloading RfP:04/09/2019, 04:00 PM to 31/10/2019, 02:00 PM
Date and time of Pre-Bid Meeting: 13/09/2019, 03:00 PM
Last date and time of submission of Envelope-1: 31/10/2019, 03:00 PM
Last date and time of submission of on-line Bid through e-procurement portal31/10/2019, 04:00 PM
Date and time of opening of Envelope-1 31/10/2019, 04:00 PM
Date and time of opening of Cover-1 & Cover-2 (on-line)01/11/2019, 04:00 PM

Important Downloads:

Reference:

This is just for simplification. Readers are requested to check with official site for updated information. Though we try to be as accurate as possible, Yellow Haze is not responsible for any error in information.